(Solved): Q-3) Samples of cight bolts are taken periodically, and their diameters (in m ...



Q-3) Samples of cight bolts are taken periodically, and their diameters (in mm) are measured. The following table presents th???????

Q-3) Samples of cight bolts are taken periodically, and their diameters (in mm) are measured. The following table presents the means, ranges, and standard deviations for 25 consecutive samples. The means are and a) Calculate the control limits for the chart. Sketch Control chart. Is the variance under control? If not, delete the samples that are out of control and re-compute and . Sketch the new chart. b) Based on the sample range , ealculate the control limits for the chart. Sketch the chart. Based on the limits, is the process mean in control? If not, when is it first detected to be out of control? c) Based on the Western Electric rules, is the process mean in control? If not, when is it first detected to be out of control? d) Repeat above parts a, b, and c, using the chart in place of the chart.


We have an Answer from Expert

View Expert Answer

Expert Answer


a) To calculate the control limits for the R chart, we use the following formulas:UCLR = D4R = 0.2877LCLR = D3R = 0.1783Where D4 = 3.267 and D3 = 0 fo
We have an Answer from Expert

Buy This Answer $5