(Solved): Please Answer ASAP Hahn Company uses a job-order costing system. Its plantwide predetermined overhea ...



Please Answer ASAP

Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the alloca
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers per hour. During the year, the company started and completed only two jobs-Job Alpha, which used 61,700 direct labor-hours, and Job Omega. The job cost sheets for these two jobs are shown below: Required 1. Calculate the plantwide predetermined overhead rate. 2. Complete the job cost sheet for Job Alpha.


We have an Answer from Expert

View Expert Answer

Expert Answer


Answer(1)Plantwide predetermined overhead rate$9.50per DLHWorking Note:Plantwide predetermined overhead rate=Job Omega's manuf